How to manage commercial construction contracts on farms
© Tim Scrivener Construction on farms is covered by a raft of legislation, not only on health and safety and work quality standards, but in the case of substantial contracts, payment obligations of which many may not be aware.
Some of these relate to payment and if the proper procedures are not followed, it can lead to large amounts of money having to be paid out unexpectedly.
“The bigger the project and the more formal the contractor, the more sophisticated (and potentially one-sided) the contract documents will be,” says Alastair Govier, a commercial litigation and dispute resolution partner with law firm Thrings.
See also: Pitfalls of farm building projects
“Often, with smaller projects and contractors, things are less formal, which can be fine if things go right, but increases the risk if things go wrong, which they often do in construction.”
Delay to completion of the works is a frequent cause of additional cost, and can have knock on effects to the farm’s operations.
Many issues can delay construction work, including the weather, delivery or material availability problems, as well as labour matters.
Variations of the works is also a common cause of additional cost and delay.
“The chief documents are the construction contract, the design drawings and specification, a quote against that specification and an agreed programme of works with an agreed completion date.
“Then when there is a delay or you have to vary it (which is the case in most construction work of any size) there is a formal agreed process to be followed and you know what is an additional cost and who is responsible,” says Alastair.
Most larger projects work on staged payments, either at monthly intervals or at naturally appropriate points such as completion of key milestones, such as of the groundworks, foundations, steelwork, cladding and fitting out the inside of a building.
Default staged payments
The payment terms for any job should be set out in the contract. However, for construction contracts over 45 days, if they are not or they are inadequate, the Housing Grants, Construction and Regeneration Act 1996 (as amended) will imply a default staged payment mechanism, known as the “Scheme”.
This is commonly referred to as the Construction Act and not only provides a default payment mechanism, with strict deadlines for payment of the contractor of each staged payment, but also provides contractors with a statutory right to suspend works for non-payment, and the parties with an automatic right to adjudication of a dispute under any contract that qualifies as a construction contract under it, including demolition.
The act came into being because, until its inception, construction disputes over issues such as payment and defective works tended to be lengthy, often causing cashflow problems for contractors and sometimes putting them out of business as a result of the customer withholding payment, says Alastair.
“It has been in force for 30 years now, but it is surprising how it still catches out both clients and contractors, including the farmer who is unaware until they face a threat of adjudication from a contractor.”
Staged payments
Alastair Govier of Thrings outlines the process for administering staged payments under the default payment mechanism in the scheme:
- The contractor must apply for payment for the value of the works carried out by it for each 28 day period
- The due date for each stage payment is the later of seven days following the end of that stage or when the contractor applies for payment
- The paying party (here the farmer) must issue to the contractor, within seven days of that due date, a payment notice setting out the sum they consider is due and the basis on which it is calculated, having measured the works carried out. If they do not do so, the contractor can serve a default payment notice (sometimes in the form of an invoice for the full amount claimed)
- The final date for payment for that stage’s work is 17 days later. This is the date by which the contractor must be paid the amount set out in the payment notice or default payment notice.
If the paying party intends to pay less than the sum specified in the payment notice or default payment notice (for example, if there is defective work), it must serve a pay less notice no later than seven days before the final date of payment, failing which it must pay the full amount stated in the payment notice or default payment notice.
Rapid process
Adjudication is a rapid dispute determination process, starting and finishing within 28 days from a notice of adjudication being served by either party.
It involves the appointment of a construction specialist as adjudicator, often a person qualified through the Royal Institution of Chartered Surveyors (Rics) or a suitably qualified engineer who decides the dispute.
An adjudication decision is enforceable through the courts.
Withholding payment of a contractor without adhering to the strict process and time-limits set out in the contract or the Scheme in a construction dispute is a classic mistake, says Alastair, and can lead to the instigation of an adjudication by an aggrieved contractor (often referred to as a “smash and grab adjudication”).
Adjudication process
Construction adjudication begins with either the employer or the contractor issuing a notice of adjudication because a dispute over issues such as what payment is due, or the quality of the work, has not been resolved.
The adjudicator is then appointed within a week of service of the notice. The claiming party then has to submit its written claim and all the evidence (including witness and expert evidence) on which it relies within seven days; the defending party then has (usually) seven days to serve its defence and evidence.
Sometimes the adjudicator will allow the claimant a right of reply – the adjudicator will then issue their binding decision within 28 days of the initial notice of adjudication.
The decision is final and binding on the parties, must be complied with and can be enforced through the courts.
In certain circumstances, the issue in dispute determined by the decision may be later reviewed afresh by a court or an arbitrator if it remains in dispute.
This is why, in adjudication of interim payment disputes, it is known as “pay now, dispute later”.
It can be an expensive process, warns Alastair, and a party’s legal costs are usually not recoverable by the winner from the loser.
Insurance
Farming businesses are generally insured only for the business of farming and as a landowner/occupier, including a compulsory element of public and employment liability, so any proposed construction work should be notified to the farm’s insurer or broker.
Once construction begins, insurance of the site should be the responsibility of the contractor until it is handed back to the farm on completion of the project.
The construction contract should set out the contractor’s insurance obligations.
The building contractor should be required to have a contractors’ all risk policy, in addition to compulsory public and employer’s liability insurance.
A designer, surveyor or other professional consultant should have professional indemnity insurance.
Alastair advises that employers of contractors should have sight of the contractor’s insurance, which should ideally be on an all-risks basis.
He also suggests getting experienced legal input in the drafting of the construction contract, as the contractor will often present its own terms which are often drafted in its interests.
Employing a contract manager is usually advisable, someone experienced in navigating contracts, works and dealing with contractors and the staged payment application process.
Payment for this service is typically on a percentage of the project cost, a fixed fee, or on a time spent basis.
Health and safety
Health and safety must be managed throughout all stages of a building project, from conception, design and planning through to site work and subsequent maintenance and repair of the structure.
The law on this applies to all work building projects and refurbishments, but not to an individual’s domestic dwelling such as a farmhouse. However, it does apply to refurbishment of any accommodation provided to employees.
All building work involves risk and proper controls must be in place, points out the Health and Safety Executive in its guidance on building work on farms.
The person employing the building contractor has overall responsibility for the health and safety of all those on site, and construction brings added risks and obligations.
“Working at height is a particular issue on farms, especially where this involves old roofs which is high risk. Ensure you have done a risk review and are taking steps to mitigate the risks.
Also, if a site is not clearly delineated, this can lead to problems.”
What is adjudication?
Adjudication is method of resolving a construction dispute without going to court, with the parties appointing an independent decision-maker who often is a lawyer or construction professional to examine a situation and decide on a dispute or disputes between the parties.
The right to adjudication overrides contracts which offer lesser terms and can be instigated at any point in a project.
It arises because payment delays and lengthy disputes through the courts or arbitration could further delay work or risk contractors (often subcontractors) becoming insolvent while disputes continue.
Employing building contractors – H&S requirements
Both the farmer customer and the contractor have legal duties for health and safety that cannot be passed to each other by contract.
The Construction (Design and Management) Regulations 2015 (CDM) are the main legal framework for managing health, safety, and welfare on all construction projects in the UK.
These apply to all building work from the initial design phase through to completion, with the aim of minimising risks to everyone involved.
The legal duties under the CDM Regulations on the client of a building contractor include:
- Allowing adequate time for every stage of the work
- Providing relevant information about the site, including existing structures and the intended use of any new workplace buildings
- Checking suitable management arrangements are in place during every stage of work
- Making sure there are adequate welfare facilities on site before work begins.
If the construction work will last more than 30 days or involves more than 500 person days, then a principal contractor must be appointed, a health and safety plan must be in place and a health and safety file kept.
Further HSE advice on farm building work covers the management of work involving asbestos, excavation and demolition or dismantling, also planning a new farm building.
Source: HSE
