The Department of Energy & Climate Change has announced plans to introduce interim “cost control measures” for the Renewable Heat Incentive in a bid to avoid the surge in demand that affected the Feed-in Tariff scheme.

The proposals, due to be in place by the summer, would see the RHI suspended until the next financial year should estimated spending – based on applications and accreditations – reach a level where the budget could be exceeded.

A total of £864m of government spending has been made available for the RHI (including the RHPP) over four years until 2014-15, with separate budgets in each financial year – £133m in 2012-13, £251m in 2013-14 and £424m in 2014-15. DECC estimated total RHI expenditure in 2012-13 would be well below the trigger for any budgetary controls at around £40m, but said unspent money could not transferred from one year to another.

Only new applications to the RHI would be affected by the changes and those already accredited would continue to receive payments if the scheme was suspended. DECC also said applications submitted to Ofgem prior to any suspension would be processed as normal.

The industry is likely to be given just one month’s notice of the temporary suspension of the scheme, if 80% of the available budget is expected to be spent. DECC said it would publish regular updates on the budget spend to give industry prior warning.

The consultation on these interim measures closes on 23 April 2012. A separate consultation on longer-term cost control measures will be launched in the summer, with measures likely to come into force from February 2013. This will also include amendments to the existing scheme covering air quality and biomass sustainability issues.